Applying for an SLF in Indonesia: Which Inspections and Technical Records Must Be Ready?

For an existing business building’s first Sertifikat Laik Fungsi Bangunan Gedung (SLF), Indonesia’s building fitness certificate, prepare the approval records, technical plans, and available as-built drawings for a site assessment. The building’s approval history determines which procedure applies. The business operator must obtain the SLF before using the building.

Establish the building’s approval history

Find out whether the building has a Persetujuan Bangunan Gedung (PBG), a building approval, or an Izin Mendirikan Bangunan (IMB), the former building permit. Check what the approval covers and whether the building has been altered since it was issued. If a copy is missing, establish whether an approval was issued. Under Article 282(12) of Government Regulation No. 16 of 2021, the assessor may use technical plans or as-built drawings as evidence when the PBG document is unavailable. See the guide to checking building approvals and fitness certificates for the permit-history check.

Articles 210–212 of Government Regulation No. 16 of 2021 distinguish the first-SLF assessment for an existing building with a PBG from the assessment for one without it. In the latter case, the assessor checks the building’s condition against technical standards and recommends and verifies adjustments where the standards are unmet. Article 286(2) provides for concurrent PBG and SLF processing through Sistem Informasi Manajemen Bangunan Gedung (SIMBG), the building management information system, in the general case of an existing building without a PBG.

Article 123 of Government Regulation No. 28 of 2025 provides a direct SLF application route for business operators who own the building. It applies when they apply for or extend business licensing, supporting business licensing, or both through Online Single Submission (OSS). Paragraph (1) allows direct application without obtaining a PBG if the building was already standing without an IMB or PBG before the regulation took effect on June 5, 2025. Paragraph (2) covers an existing building with an IMB or PBG in the same licensing context. If the intended use is changing, also check the site’s spatial-use conditions.

Arrange the assessment and gather the drawings

Under Article 122 of Government Regulation No. 28 of 2025, an existing business building is assessed by a Pengkaji Teknis (technical assessor) or a technical assessment team formed by the local government with relevant agencies. A certified technical assessment provider is one route for an existing building with a PBG. Establish who can commission the assessment for the building and whether a local-government team route applies. Government Regulation No. 16 of 2021 provides for assignment by the owner or user under a work contract.

For the assessment, gather the general building data, owner identification, applicable approval and technical plan, construction documents or as-built drawings, and relevant maintenance records. As-built drawings show what was actually constructed. Article 282(13) sets minimum safety details for those drawings, including beam and column dimensions and locations, evacuation routes, fire and lightning protection, and electrical installations. When a drawing is missing or obsolete, ask the assessor what supporting evidence to recover and what they need to verify on site.

Jakarta’s public building-system FAQ gives local examples of architectural plans and sections, structural drawings, and building-services schematics. Some of those categories carry qualifications, so confirm which apply to the building in Jakarta.

Compare the site with the drawings and approval

Table IV.21, Luas Total Lantai Bangunan Gedung (total building floor area), in Government Regulation No. 16 of 2021 is a blank assessment form. Its first column records the actual measured area in square meters. In the second, the assessor compares the actual condition with the technical plans and as-built drawings. The form provides boxes for Sesuai (conforming) or Tidak Sesuai (nonconforming), with space to describe any difference. Official floor-area inspection form, page 2047

Suppose the assessor measures 1,080 square meters in an existing warehouse with a PBG. The measurement includes a mezzanine that the as-built drawings omit. Those drawings show 1,000 square meters. After recording the measured area and the discrepancy, compare the mezzanine with the approved plan. That check helps the assessor identify any departure from the approval and any drawings that need updating. For a facility used for storage, check the separate warehouse registration rules based on how the warehouse is used.

Act on the assessor’s findings

For the first SLF of a building with a PBG, Article 211 calls for checking document completeness, comparing the as-built drawings, approval, and site against technical standards, then evaluating the findings and preparing a report and recommendations.

  • If the as-built drawings differ from the PBG and the building meets technical standards, the assessor prepares a report and recommends applying for a PBG amendment.
  • If the as-built drawings match the PBG and minor damage requires maintenance and care, the assessor prepares a report and recommends that work.
  • If the as-built drawings differ from the PBG and the building fails technical standards, the assessor prepares a report and recommends adjusting the building and applying for a PBG amendment.

Under Article 211(5), the assessor verifies the maintenance and care or adjustments carried out by the owner or user in the relevant cases. Keep the report and the evidence of work together for that verification. Where the findings support one, the provider also issues a building fitness statement under Article 283.

Follow the application through official verification

Under Article 285, the owner submits the existing building’s application to the technical department. If the documents are incomplete, the department gives the owner notes on what to supply. It verifies the documents and compares the site with the assessment report. If it finds inconsistencies or false information, it issues a written refusal and the application for the statement of compliance with technical standards must be repeated.

Article 286 places the technical department’s statement of compliance through SIMBG before certificate issuance. Under Article 122 of Government Regulation No. 28 of 2025, the ministry responsible for public works or the relevant local technical department issues the SLF through OSS, according to its authority. Before operating, check the licenses needed for the business activity alongside the building’s approvals.