KKPR in Indonesia: When Do You Need Confirmation or Approval?
For an ordinary new land-based business site, apply for spatial conformity confirmation when an integrated detailed plan covers the whole proposed footprint. Apply for approval when the site has no detailed plan or lies wholly within a plan that has yet to be integrated. The outcome depends on how the proposed use fits the rules at that location.
Check the plan against the whole site
Kesesuaian Kegiatan Pemanfaatan Ruang (KKPR) is Indonesia’s spatial conformity requirement. Article 15 of Government Regulation No. 28 of 2025 sets out two ordinary routes for land. Konfirmasi Kesesuaian Kegiatan Pemanfaatan Ruang (KKKPR) is confirmation, and Persetujuan Kesesuaian Kegiatan Pemanfaatan Ruang (PKKPR) is approval. Government Regulation 28/2025, Article 15
Find the Rencana Detail Tata Ruang (RDTR), or detailed spatial plan, for the site. Check its boundaries, what it allows for your activity, and whether it is integrated into the Sistem Perizinan Berusaha Terintegrasi Secara Elektronik, or Online Single Submission (OSS). If the public map has no integrated coverage at your location, ask the local spatial planning office whether an adopted detailed plan already covers it. Public OSS map · Reading the detailed plan and zoning rules
Compare three sites for the same warehouse
Suppose a company is comparing three sites for a one-story warehouse that stores packaged household goods. The proposed use, layout and land area are the same at each site.
| Plan status for the whole site | Route and next check |
|---|---|
| An RDTR integrated into OSS covers the entire site. | Apply for KKKPR under Article 17. OSS issues confirmation automatically if the proposal conforms to the plan and refuses it automatically if it does not. |
| No RDTR covers the site. | Apply for PKKPR under Articles 18–24. The authority checks the documents and assesses the proposal against the applicable spatial plans. This assessment ordinarily considers the technical land review. |
| An existing RDTR covers the whole site and has yet to be integrated into OSS. | Apply for PKKPR under Article 25. The authority assesses the proposal against the applicable spatial plans and considers the RDTR. This branch proceeds without a technical land review. |
Confirmation and approval, Articles 17–19 · Ordinary approval assessment, Articles 21–22 · Approval under an unintegrated plan, Article 25
Both approval cases involve registration, a document check and a spatial assessment. Follow payment notices and requests to correct documents in OSS. If the authority refuses the proposal, OSS gives the reasons. In the no-plan case, Article 22(3) allows issuance to proceed without the technical land review if it is missing from the assessment at the statutory deadline. The authority still assesses spatial conformity. Approval without a timely technical land review, Article 22(3)
If OSS automatically refuses confirmation, you can look for another site that fits the plan or ask the responsible planning authority for coordination or consultation. The resulting recommendation can support confirmation if the review finds that the proposed location and use conform to the plan. Investment Ministry Regulation 5/2025, Article 48
Check boundaries and special routes
If an integrated plan covers only part of the proposed site, take the full site polygon to the competent spatial planning office. Ask which route applies to each part and check the area covered by each document issued.
If the site crosses a regency, city or provincial border, check the separate rules for sites that cross administrative boundaries. Those rules distinguish one contiguous area from separate tracts. Investment Ministry Regulation 5/2025, Articles 60–62
A business that qualifies as both micro and low risk may use the OSS self-declaration route if the operator is an individual or single-person company and meets the applicable conditions. The operator submits site data and a declaration, which the competent authority reviews for spatial conformity. Government Regulation 28/2025, Articles 32–33 · Investment Ministry Regulation 5/2025, Article 67
Some special economic zones and industrial estates qualify for approval without the ordinary spatial assessment. The zone or estate’s polygon must be registered in OSS, and the applicant must show it may carry out the proposed activity there. The authority still checks the proposal documents. If you are buying or leasing a site with an existing approval, check whether it covers your project and transaction. Government Regulation 28/2025, Article 27 · Checking an existing approval for a purchase or lease
Prepare the site details before applying
For either ordinary route, gather the location coordinates, land area needed, land-control information and proposed activity. Prepare the planned number of stories and floor area, and the technical building plan, the area master plan, or both. The public OSS guide shows where to upload the polygon outlining the proposed site for confirmation. Use the actual activity and its Klasifikasi Baku Lapangan Usaha Indonesia (KBLI), the Indonesian business activity classification. Official OSS confirmation guide · Choosing business activity codes
When OSS issues a confirmation or approval, compare its activity, location and approved area with what the business plans to use. Check any other permissions the business still needs before operating. Business registration and operating readiness