Must a Factory Be Located in an Industrial Estate in Indonesia?

Industrial companies starting industrial activities in Indonesia generally must locate in an industrial estate, unless they qualify for a specific exception. Before committing to a site outside an estate, establish the applicable exception, the site's spatial designation and any required location verification. An exception leaves environmental and operating requirements in place.

Distinguish an Industrial Estate From Industrial Zoning

A Kawasan Industri, or industrial estate, concentrates industrial activities within an area developed and managed by an industrial-estate company, with supporting infrastructure. Kawasan Peruntukan Industri (KPI) means land designated for industry under the applicable spatial plan. A plot can be within KPI without belonging to a managed estate.

Government Regulation 20/2024, Article 62 sets the estate-location rule and exceptions. Government Regulation 28/2025, Article 151, and Minister of Industry Regulation 37/2025 provide the current licensing framework and implementation.

When Can a Factory Locate Outside an Estate?

The table maps Article 62 to the current implementation in Regulation 37/2025, Articles 16–19.

Article 62 exception What the current rule requires Remaining location condition
District/city has no industrial estate: 62(2)(a) The relevant district/city has no estate. The factory must be in KPI under the spatial plan.
District/city has a special economic zone with an industrial zone: 62(2)(b) Regulation 37/2025 specifies location inside the industrial zone of that special economic zone. Merely being in the same district/city is insufficient. Inside that industrial zone; see the Article 62(4) distinction below.
All industrial plots in the district/city's estates are exhausted: 62(2)(c) Article 16(5) includes insufficient plot area for the company's needs or an activity not covered by the estate's environmental impact assessment. The factory must be in KPI.
Small industry: 62(3)(a) The business must actually meet the applicable small-industry classification. Applicable spatial requirements remain; see the distinction below.
Medium industry without potential for widespread environmental pollution: 62(3)(b) Article 18 defines this by whether the industrial activity is not required to have an environmental impact assessment. The factory must be in KPI.
Special raw materials and/or a production process requiring a special location: 62(3)(c) Article 19 and Annex III identify the conditions and listed activities. Follow the applicable location conditions and zoning directions.

Article 62(4) expressly applies the KPI requirement to the three paragraph (2) groups and the medium-industry group. Article 151(3) of Regulation 28/2025 and Article 16(3) of Regulation 37/2025 expressly restate KPI for the no-estate, exhausted-plots and medium-industry routes; the special-economic-zone route requires its industrial zone.

These KPI clauses do not expressly include the small-industry and special-input/process groups. Their exceptions do not authorize manufacturing on any available plot. Article 62(5) also assigns ministerial determination of the paragraph (3) industries; the category labels are not self-issued permissions.

Establish the Activity Behind the Exception

Start with Klasifikasi Baku Lapangan Usaha Indonesia (KBLI), Indonesia's business activity classification, and the actual production process. Use the guide to choosing KBLI codes from real business activities to separate the proposed work from a property's advertised use. A small building does not establish small-industry classification. Foreign-invested companies should establish their applicable investment and industrial scale classifications before relying on that row.

For the medium-industry route, determine whether Analisis Mengenai Dampak Lingkungan Hidup (AMDAL), the environmental impact assessment, is required under the applicable environmental rules. Describing a process as clean does not answer that statutory test.

For special raw materials, Article 19 covers materials from agriculture, plantations, fisheries and/or livestock. It requires one or both of these connections:

  • An industrial site integrated with the raw-material operation, or near it with supporting infrastructure.
  • A value-chain link with the raw-material operation on one tract, or on separate tracts connected by physical infrastructure for moving materials.

The activity must also match Annex III.

The annex gives actual zoning directions: fish fermentation under code 10215 is directed to coastal/fisheries areas. The special-process route also includes certain industrial services without a need for wastewater-treatment or raw-water-treatment infrastructure. Neither route is a general waiver based on business convenience.

Check Existing-Site Documents Before Relying on Them

Article 17 contains additional cases. One concerns land controlled by another business that already obtained spatial conformity, then transferred, leased or lent to a new operator with the same KBLI, activity type and area. An old factory address alone does not meet those conditions.

Article 17 also covers an existing industrial license holder adding another industrial activity within the same business-activity group; a change in industrial scale classification without additional land or relocation; and an operator that already holds licensing to start business in another sector and changes to industrial licensing under the applicable law.

Article 23(b) covers businesses that already held spatial-conformity documents before the regulation took effect on October 5, 2025. It lets those businesses continue their industrial licensing applications without industrial-location conformity verification. Check the holder and scope as well as the document date before relying on this transitional provision.

Obtain the Location Verification

Article 20 requires verification through Online Single Submission (OSS), the integrated electronic licensing system, for the exceptions in Articles 16(2) and 17. The Ministry of Industry director responsible for industrial regional development verifies the exception application within a maximum of five working days.

If the criteria are met, the director approves through OSS. The approval notification lets the applicant continue the subsequent basic-requirements process. If refused, the applicant cannot continue that process. The five-day verification provision does not make silence an approval or establish a five-day deadline for full operating permission.

Keep the application and resulting notification with the site decision. Article 20 does not itself prescribe a universal exemption certificate or attachment checklist.

Resolve the Site Evidence Before Committing Funds

Before signing or paying, request evidence suited to the proposed route:

  • Identify the plot boundaries, proposed activity and industrial classification, then compare them with the spatial designation and existing documents.
  • For an exhausted-plots argument, establish the relevant estates' availability and the specific area or environmental-scope constraint. A preferred estate's quotation alone does not establish the district/city-wide condition.
  • For an exception, retain the facts supporting the precise provision and the required OSS result, or the basis for a relevant transitional treatment.
  • For an estate plot, obtain the estate rules and applicable tenant requirements. Articles 63–64 retain environmental, spatial and industrial licensing obligations. Article 63's explanation uses the estate's spatial conformity rather than a new spatial-conformity approval.

These are practical evidence requests, not a newly prescribed government document list. For estate tenants, Article 63 specifically requires detailed environmental management and monitoring plans approved by the estate company or manager, with additional technical approval for the specified hazardous-waste activities.

Nomor Induk Berusaha (NIB) is the business identification number. Review whether an NIB is enough to operate alongside the site's remaining requirements. If a proposed lease depends on an exception approval that is still pending, address that dependency and the payment consequences in the contract before committing funds.